Stirling Schools PPP
|
Contract Value
|
£650,000
|
|
Contract Period
|
July 2007 – May 2008
|
|
Contract Form
|
SBCC Minor Works Contract (2006)
|
|
Client
|
Stuart Milne Construction
|
|
Engineer
|
Dougal Thornton
|
Land Engineering was appointed as a specialist sub-contractor to design and construct the pitches at the new Wallace High School in Stirling. This comprised of one third-generation full-size football pitch and two full-size grass pitches.
Activities
- Ground remediation.
- Drainage.
- Full-size synthetic pitch.
- Two natural grass pitches.
- Sports equipment installation.
- Floodlighting.
- Perimeter fencing.
Outcome
Our work was completed successfully and as budgeted for in time and cost.
Download Case Study
Click the link below to download the pdf